Lucite 90000 ton MMA expansion project environmental impact assessment publicity

Lucite's characteristics of these coatings include: the wavelength of reflected light can be changed through the film. 90000 ton MMA expansion project environmental impact assessment publicity

June 3, 2011

[China paint information] release unit: Shanghai Environmental Protection Development Co., Ltd.

release date: June 1, 2011

1 Description

Sinopec Ningbo Engineering Co., Ltd. and Shanghai Environmental Protection Development Co., Ltd. were entrusted by Lucite International (China) Chemical Co., Ltd. to carry out the environmental impact assessment of the 90000 ton MMA expansion project of Lucite International (China) Chemical Co., Ltd. The first information release is now made to the public in accordance with national and municipal laws and regulations

Lucite International (China) Chemical Co., Ltd., Sinopec Ningbo Engineering Co., Ltd. and Shanghai Environmental Protection Development Co., Ltd. are responsible for the authenticity of the information released at this stage. As the project implementation process and evaluation work are carried out, relevant information will be improved or adjusted

2. Summary of construction project

(1) project name:

90000 ton MMA expansion project of Lucite International (China) Chemical Co., Ltd.

(2) project location:

Shanghai chemical industry, Caojing, Shanghai, but until about 15 seconds, plot a of the park

(3) industry of the project: chemical industry

(4) project content:

Lucite International (China) Chemical Co., Ltd. will expand and transform the existing MMA plant, From the original 90000 T/a MMA to 180000 T/A, the raw material HCN is still from SECCO's acrylonitrile plant, and the acetone cyanohydrin (ACh) process route is still used. The plant does not expand the land occupation, and the plant capacity is doubled by replacing and transforming some existing equipment. The total investment of the project is 316.1038 million yuan

3. Overview of the construction unit

(1) name of the construction unit: Lucite International (China) Chemical Co., Ltd.

(2) address of the construction unit: 26F, Meiluo building, No. 30, Tianyaoqiao Road, Xuhui District, Shanghai

postal code: 200030

(3) contact person of the construction unit: Xu Liang

(4) contact information of the construction unit:

4 Summary of the evaluation organization

(1) name of the evaluation organization: Sinopec Ningbo Engineering Co., Ltd.

Shanghai Environmental Protection Development Co., Ltd.

(2) certificate number of the evaluation organization: National Environmental Assessment Certificate a No. 2006

National Environmental Assessment Certificate B No. 1805

(3) address of the evaluation organization: No. 660, academician Road, national high tech Zone, Ningbo

16th floor, No. 9, Huangpi North Road, Shanghai

(4) Contact person of evaluation organization: cold worker

(5) contact information of evaluation organization:

guoyiwen443@

5. Environmental impact assessment procedures and main work contents

(1) environmental impact assessment procedures and main contents of the project

preparation stage

research related documents: including national and local laws and regulations, development planning and functional zoning, technical guidelines and relevant standards, construction project basis, feasibility study data and other relevant technical data

preliminary engineering analysis: clarify the engineering composition of the construction project, and determine the pollution discharge links and main pollutants

investigation on the current situation of environmental quality in the environmental impact area of the construction project

combined with preliminary engineering analysis and environmental quality status survey data, identify the environmental impact factors of the construction project, screen the main environmental impact assessment factors, and clarify the evaluation focus

further engineering analysis in the formal work stage: conduct sufficient investigation, monitoring and evaluation of the current situation of environmental quality

predict the environmental impact of the construction project according to the source strength and environmental quality status materials, evaluate the environmental impact degree of the construction project, and carry out public investigation

propose environmental management measures and engineering measures to reduce environmental pollution and ecological impact

in the preparation stage of the environmental impact report,

summarize and analyze the information and data obtained in the second stage, determine the feasibility of the project construction from the perspective of environmental protection, give evaluation conclusions and put forward environmental protection measures and suggestions to further mitigate the environmental impact

prepare the environmental impact report

(2) key points of environmental impact assessment

according to the nature and characteristics of the project construction, this assessment will focus on engineering analysis and environmental risk assessment

6. Main matters for soliciting public opinions

in order to listen to the opinions and suggestions of all sectors of society on the environmental protection work of the project, the information of the project is publicized to solicit valuable ideas and suggestions from the public. The main contents are as follows:

(1) public support for the construction of the project

(2) opinions on the main environmental problems of the project construction and the possible impact on the surrounding environment

(3) environmental protection measures and environmental management opinions or suggestions for the construction of the project

(4) other ideas and suggestions on environmental protection

7. Public feedback methods

from now on, the public can express their views on the construction project and environmental assessment work by sending e-mails, letters, etc. to the construction unit and the assessment institution (issues unrelated to the environment are not accepted)

the environmental impact assessment unit will truly record the public's opinions and suggestions in the environmental impact report of the project, and reflect the public's valuable opinions and suggestions to the construction unit, design unit and relevant departments of the project

this project has carried out two EIA announcements at this station. This is the first announcement. Before submitting the EIA report to the competent administrative department of environmental protection for approval or re examination, the second EIA announcement will be carried out at this station. At that time, if there is any difference in the heating method of the plastic granulator, please pay attention to the simplified environmental impact report

8. Effective period of information release

within 2 weeks from the date of this information release, the public can express their views on the project construction and environmental high-quality product evaluation by sending e-mail, fax, letter or interview to the designated address