Environmental impact assessment of Shanghai waterb

2022-08-12
  • Detail

DuPont high performance coating (Shanghai) water-based coating mixing plant project EIA publicity

DuPont high performance coating (Shanghai) is expected to be 200000 (2) 50000 tons of water-based coating mixing plant project EIA publicity

August 9, 2011

[China coating information] release unit: Shanghai Academy of Environmental Sciences

release date: August 9, 2011

1 Description

Shanghai Academy of Environmental Sciences is entrusted by DuPont high performance coatings (Shanghai) Co., Ltd. to carry out environmental impact assessment on the water-based coating mixing plant project of DuPont high performance coatings (Shanghai) Co., Ltd. (hereinafter referred to as "the project"). The first information release is now made to the public in accordance with national and municipal laws and regulations

DuPont high performance coatings (Shanghai) Co., Ltd. and Shanghai Academy of environmental sciences are responsible for the authenticity of the information released at this stage

with the implementation process of the project and the implementation of environmental impact assessment, relevant information will be completed. 13. The sample will be damaged or adjusted

2. Outline of the construction project

(1) project name: DuPont high performance coatings (Shanghai) Co., Ltd. water based coating mixing plant project

(2) project location: No. 3199, Shengxin North Road, Jiading Industrial Zone, Shanghai. DuPont factory has an existing small batch production workshop

(3) industry of the project: industry category chemical raw materials and chemical products manufacturing, C2 before use 6

(4) project content: the total investment of the project is US $1million, and the main product is a new generation of water-based paint, with an annual output of 800t/A. The project is built in DuPont's existing small batch production workshop, and the original plant of DuPont factory is used for reconstruction. The main utilities and environmental protection projects rely on existing equipment

3. Overview of the construction unit

(1) Name: DuPont high performance coatings (Shanghai) Co., Ltd.

(2) contact address: No. 3199, Shengxin North Road, Jiading Industrial Zone, post code: 201815

(3) contact person: Cheng Jincheng

(4) contact:, Fax:

e-mail:eng@

4 Outline of the evaluation organization

(1) Name: Shanghai Academy of Environmental Sciences

(2) Certificate Number: National Environmental Assessment Certificate Jia Zi No. 1801

(3) address: No. 508 Qinzhou Road Post Code: 200233

(4) contact person: Zhu Gong

(5) contact information: (fax)

e-mail:zhuhs@

5. Working procedures and main work contents of environmental impact assessment

according to the relevant technical guidelines of environmental impact assessment.Requirements, Prepare environmental impact statement. The emphasis of environmental impact assessment is determined according to the content and characteristics of the construction project

working procedure of environmental assessment of the project: Based on the investigation of the current situation of environmental quality and the analysis of the project engineering, according to the prediction results of environmental impact, combined with the investigation results of public participation, the evaluation conclusion of the environmental feasibility of the project is given, and the environmental protection measures and suggestions are put forward

the main contents of the environmental impact assessment of the project include: (1) analysis of project sewage discharge; (2) Investigation and evaluation of regional pollution sources and environmental quality status in the project area; (3) Environmental impact assessment of the project (atmosphere, noise, solid waste, surface water); (4) Compatibility analysis between project and planning; (5) Public participation; (6) Environmental impact analysis during the construction period; (7) Comment and rationality demonstration of environmental protection measures (8) environmental risk assessment; (9) Pollution control countermeasures; (10) Environmental management and monitoring plan; (11) Evaluation conclusion

6. Main matters for soliciting public opinions

this publicity mainly solicits public opinions and suggestions on the environmental protection of the project construction, and the main contents include:

(1) the main environmental problems currently existing in the project area

(2) the main environmental problems of the project and the possible impact on the surrounding environment

(3) thoughts and suggestions on environmental protection of the project

(4) attitude and suggestions on the construction of the project

7. The public puts forward the main ways to clean and grind ink or reduce the troubleshooting of oil grooves

after this information publicity, the public can send e-mail, fax, letter and other means to the construction unit and evaluation institution to express their opinions on the construction of the project and environmental assessment work (only accept the problems related to environmental protection). Please refer to Article 3 and 4 for contact information. Please leave your real name and basic information (unit or address, education level, occupation, contact information, etc.) as far as possible for public comments, so as to feedback as needed and make a return visit if necessary

8. Effective period of information release

the effective period of this information release and public consultation is 10 working days from the date of this release, and the postmark date shall prevail for letters)

Copyright © 2011 JIN SHI